Oil & Gas

Kvaerner Nyhamna Expansion Project

Case study

Client

Kvaerner

Location

Nyhamna Onshore Gas Plant

Individual Units Weight

Up to 886Te

Overall Weight

4,300Te

Project Scope

OGN will fabricate a series of 18 Pre-Assembled Units (PAUs) for the Shell-operated onshore plant. The project will increase the capacity of the facility to allow gas from other fields to be processed.

Project Profile

The plant is today connected to the Ormen Lange gas field 120km off the west coast of Norway. Ormen Lange was developed as a subsea tie back to the Nyhamma Gas Plant where the gas is dehydrated, hydrocarbon dew-pointed and compressed. Gas is exported through the Langeled Pipeline to gas markets in the UK.

Award Date

May 2014

Load Out Date

Autumn 2015